Photovoltaic risk

Photovoltaic activities highlight two types of risk:

  • the uncertainty of actual acquisition of the incentive tariffs and their assessment for “large” plants subject to the registration procedure;
  • the inability to calculate authorisation times, especially the timing of connection to the electricity network of the plants constructed, which introduces a further element of uncertainty in economic assessments, also for plants not subject to registration, particularly in consideration of the strong downward monthly trend in the value of grants envisaged for the next few years.